PES Logos

Home > Case Studies > Overhead Lines

OVERHEAD LINES

Linesmen at work

Customer:

Electricity Supply Board (ESB)

Contract:

Framework contract for the refurbishment and upgrade of distribution overhead lines

Location:

Various sites throughout Republic of Ireland

Term:

2003-06

In 2003 Powerteam was awarded a framework contract to refurbish and upgrade the ESB 10kV network in the Republic of Ireland.

  • At the height of the contract we deployed a team of over 300 staff, providing survey and design, construction and logistics management for ESB.
  • We were responsible for refurbishing 9,200km of overhead lines over the contract duration and established bases in Counties Donegal, Dublin, Sligo, Cavan and Limerick to deliver this work.

Customer:

Western Power Distribution (WPD)

Contract:

Refurbishment of 132kV overhead lines

Location:

Hayle, Cornwall

Term:

2005-06

Powerteam has completed a number of refurbishment and construction of new build 132kV tower lines in southwest England and south Wales for WPD, including Hayle phases I and II. The project scope covered:

  • Design and installation of foundations
  • Supply and erect temporary mast
  • Supply and erect tower fittings, terminate conductors and install downleads
  • Dismantle existing towers and lines and remove scrap from site
  • Acting as Principal Contractors under CDM regulations

Customer:

Scottish and Southern Energy plc

Contract:

Framework contract for the refurbishment and upgrade of low voltage distribution overhead lines

Location:

Throughout Scottish Hydro-Electric region

Term:

2006-10

Powerteam is currently undertaking low voltage overhead line network refurbishment for villages throughout the Scottish Hydro-Electric region. This work uses live line techniques requiring detailed planning, co-ordination with local authorities and liaison with customers to carry out the work both safely and efficiently. Our remit also covers the pre-work patrolling, design of solutions and actual refurbishment work together with rectifying any ESQCR line clearance issues.


Customer:

Electricity Supply Board (ESB)

Contract:

Framework contract for the refurbishment and upgrade of 38kV transmission overhead lines

Location:

Various sites throughout Republic of Ireland

Term:

2004-06

In 2004 Powerteam was awarded a two-year framework contract by ESB to refurbish over 200km of 38kV overhead lines. This covered all aspects of patrolling, survey, design and wayleaves functions, refurbishment and construction of the 38kV lines.


Customer:

AMEC

Contract:

Construction of 110kV trident overhead line

Location:

Castlereagh - Newtownards, Northern Ireland

Term:

2004

Powerteam was awarded the construction of Ireland's first major 110kV trident overhead line to be built for NIE. The line runs for 20km between Castlereagh and Newtownards in Northern Ireland and employed the patented AP1 trident construction system, with a single pole replacing conventional portal frames.


Customer:

Electricity Supply Board (ESB)

Contract:

Refurbishment of 110kV overhead line

Location:

County Limerick, Republic of Ireland

Term:

2005

In 2005 ESB awarded Powerteam the contract to upgrade and re-conductor two existing 110kV circuits in County Limerick - Limerick to Monateen and Aughinish to Monateen. Both projects significantly reinforced the network in advance of the completion of the Aughinish Alumina Power Station. The work included a mixture of changing-out existing pole sets and conductors.

top

Quality Logos

SubstationsSubstations
Overhead LinesOverhead Lines
Private NetworksPrivate Networks
Renewable SolutionsRenewable Solutions
Commissioning ServicesCommissioning
ClientsClients
Project References & PartnershipsProject References