Walney Phase 1 183MW windfarm – 132kV substation (Heysham, UK)
Scope of works includes:
- Project management and electrical design
- Civil & building works
- Installation of:
- 132kV GIS substation and equipment, including a reactor & filter bank, for ‘tail fed’ connection to the offshore windfarm.
- Control building incorporating protection, control, indication & telecommunications panels; LV a.c. and d.c auxiliary systems; tariff metering.
- LV power and and control cables
- Substation earthing grid.
- Substation building services.
- Testing & Commissioning.
Option:
Powerteam have also secured the option to construct a similar substation for Walney Phase 2 (183MW) starting Sept. 2010, for completion August 2011.