Framework agreement for the refurbishment of 110-400kV overhead lines throughout the Republic of Ireland.
Scope of work covers:
- Removal of existing 110kV conductor, installation of replacement ACSR conductor including stringing, sagging and clamping on single circuit pole sets, double circuits and double circuit towers.
- Installation of earth wire and non-earthwire structures; change tension insulators; fit anti-climbing guards, plumbing poles, install earth grids; fit stay assembly and bog shoes.
- Lift existing 110kV overhead line cross arms onto new higher pole sets; woodpole installation; re-sag and restring 220kV conductor.
- Replacement of insulators and other equipment on existing cross arms.
- Tower climb patrols/inspections.
- Provision of “as built records”
- Project Supervisor Construction Stage (PSCS) responsibility.